Read your recovery and disposal figures, tonnage and cost for any period, understand why waste shows as having no declared fate, and download the data behind it

5 min readUpdated 2026-10-26customer portalreporting

Reporting shows how much waste your waste company collected from you in a period, what it cost, and where it went. It is for customers only. If you do not see Reporting in the sidebar, the company has not shared it with you. Ask them to add it. Suppliers do not get this page.

The page describes itself in one line: fulfilled jobs only (completed, ready to invoice or invoiced), all costs exclude VAT, and tonnage uses recorded weights where they exist and estimates otherwise.

Choose the period and filters

The bar above the figures has these controls:

  • From month and To month set the period. They offer the last 36 months, and a period can be at most 36 months long. It starts as the current quarter to date.
  • Site narrows the figures to one site. It lists All sites, or only the sites the company has limited you to. A site that has been archived is shown with "(archived)" after its name.
  • Tag appears only if the company has set up lists for you, for example departments. Choose a value to see just the jobs carrying it, or All tags.

If the dates do not work you will see "Choose a start and end month.", "The start month must not be after the end month.", "The end month must not be in the future." or "Choose at most 36 months." Fix the dates and the figures return.

The period is kept in the address of the page, so reloading it or bookmarking it keeps the same range.

A job is counted in the month the waste was received. If that date is blank it falls back to the booked date, then the requested date, then the date the job was created.

Read the headline

The big figure answers one question in a sentence. It changes depending on your data:

  • "of your waste was recovered" with a percentage, when most of your waste has a known fate. The sentence under it gives the tonnes, for example that they "went to recycling, energy from waste or storage for recovery".
  • "of your waste has no declared fate yet" with a tonnage, when half or more of the waste has no recorded fate. The sentence gives the share.
  • "of your waste was weighed this period" with 0 t, when your jobs recorded only litres and no weights. There is no tonnage to split, so the page says how many litres were recorded.

Why some waste has no declared fate

The recovery and disposal split is not measured on your job. It comes from the fates your waste company has declared for the disposal site that took the waste, as percentages per waste code for a period of time. When that declaration is missing or incomplete, the waste is counted as Unknown, and the headline adds a sentence such as "(12%) have no declared fate" followed by the reasons:

  • tonnes "with no disposal site"
  • tonnes "with no fate declaration for the period"
  • tonnes "with waste codes not declared by the site"
  • tonnes "only partly declared"

That is not an error in your numbers, and you cannot fix it from the portal. Ask the company to record the fates for those disposal sites. They do that on the supplier's site record, as described in Managing Suppliers.

Read the three figures

Beside the headline are three figures: Jobs fulfilled, Tonnes collected and Cost, ex VAT. Each is compared with the previous period of the same length, and shows an arrow with a percentage, for example "▲ 12% vs Jul 2026 – Sep 2026". A rise in cost is shaded amber, because higher is worse. If there is nothing to compare with you see "No previous data" with the period, and if the figure is unchanged you see "No change since last period".

Under Tonnes collected you may see "plus" a number of litres "not converted to tonnes". That is waste recorded only as a volume, with no density, which the portal counts in litres rather than inventing a weight.

See how the fates break down

The bar under the headline splits all your tonnage across nine fates, grouped into three:

GroupFates
RecoveryRecycling, Energy from waste, Storage (R)
DisposalIncineration, Treatment, Hazardous landfill, Non-hazardous landfill, Storage (D)
UnknownUnknown

Below it the full list gives the tonnes and percentage for each fate, including those at zero.

Where your waste went draws the same journey as a flow: every tonne is split into recovery or disposal, then into its declared fate, and the width of each ribbon is the tonnes. Hover a ribbon for the figure. If every tonne in the period went to the same fate, the page says so ("Every tonne in this range went to the same fate") and the diagram appears once there is more than one.

Follow the month-by-month charts

  • Tonnes by month stacks each month's tonnes by waste type, and shows the period's total beside the heading. The largest waste types each get their own colour and the rest are grouped. The month's total is written above each column when there is room.
  • Cost by month shows the cost for each month, with the total "ex VAT" beside the heading.

Download the data or print the page

Download data saves a CSV of the detail behind the charts, one row per line, with columns such as Job number, Job date, Site, Tags, Waste type, EWC codes, Container type, Disposal site, Tonnes, Price (ex VAT) and the tonnes for each fate. It uses the period and filters you have chosen. To pick columns, click the arrow beside the button (Choose columns), tick what you want, and click Export followed by the number of columns.

The same limits as the other lists apply: 100,000 rows at most, and ten exports a minute. See Customer Portal: Your Records.

Print prints the page without the filter bar.

When the page is empty or does not load

  • "No fulfilled jobs in this range." Nothing was completed in those months. Widen the period.
  • "Couldn't load reporting" with Retry. Try again in a moment.
  • "Couldn't refresh — showing" and the period. The page is showing the last figures it loaded. Click Retry.